Field of work : Energy Production and Distribution
Location : Sousse
- Electrical Installation and Commissioning of a 6.3 MW Cogeneration Plant with
Jenbacher JMS 624 GS-NL Engine 11kV - 4500 kW:
- Mounting and connection of 2 MT 30kV cells at the Delice Holding factory in Soliman.
- Mounting and connection of Control Panel A1.
- Assembly and connection of the Auxiliary panel.
- Mounting and connection of 6300kVA Step-up Transformer.
- Supply and installation of fire detection system.
- Supply and installation of various cable sections.
- Supply and installation of different types of cable pathways.
- Supply and installation of different mounting accessories and connections.
- Testing and commissioning of the installation.
Achievements in 2016
Entretien, changement et mise en service de l’éclairage du tour Préchauffage et Tour Ensilage
Achievements in 2018
Fourniture, Installation et mise en service d’un système de sécurité Incendie (une centrale incendie conventionnel à afficheur LCD extensible à 20 zones, 14 détecteurs de fumé, 03 déclencheurs manuels, 03 sirènes conventionnelles combinée.
Achievements in 2019
Démontage et montage de poteau FRF y compris exécution d'un massif en béton
Travaux d’entretien ligne aérienne 30KV
Client : CAT COLACEM
Pays: Tunisie
Réalisations:
– Entretien, changement et mise en service de l’éclairage du tour
Préchauffage et Tour Ensilage
– Fourniture, Installation et mise en service d’un système de sécurité
Incendie (une centrale incendie conventionnel à afficheur LCD
extensible à 20 zones, 14 détecteurs de fumé, 03 déclencheurs
manuels, 03 sirènes conventionnelles combinée.